ROOF
FUND APPEAL PROGRESS REPORT 2
FROM 11 JULY 2004 TO 9 DECEMBER 2004
St Peter and St Paul, Exton, Rutland
This Report follows on
from Report 1, up to 10 July 2004, and should
be read in conjunction with it (attached below)
Funds raised (including firm promises) to date
(9 December 2004).
Fund-raising and donations within the parish
£ 12 500
English Heritage Stage 2 Grant see Note 1 below
£110 700
Grants and promises from Foundations, Funds
and Trusts:
The Alan Evans Memorial Trust
The Allchurches Trust
The Chase Charity
The Cory Environmental Trust for Rutland
The Francis Coales Charitable Foundation
The Garfield Weston Foundation
The Headley Trust
The Historic Churches Preservation Trust
The Jill Franklin Trust
The Mercers’ Company
Rutland County Council
The Rutland Historic Churches Preservation Trust
The Trusthouse Charitable Foundation
The Wolfson Foundation/Council for the Care
of Churches
£ 43 200
Refund of VAT on tender costs to be paid by
English Heritage (see Note 1) £ 18 300
Ditto ditto ditto Exton PCC £ 6 100
Ditto on ‘ineligible’ works ditto
Exton PCC £ 7 800
Less Exton PCC contribution towards
English Heritage Stage 1 (£ 3 200)
TOTAL £ 195 400
Note 1: VAT. We are reclaiming
VAT under the Listed Places of Worship Scheme.
The English Heritage Stage 2 Grant of £129
000 includes £18 300 VAT so net of that
tax it is worth
£ 110 700. It covers 75% of the high-level
work and none of the rest.
Our 25% of the cost of such (“eligible”)
work is £43 000. The VAT on that is £6
100, which we will reclaim and retain.
We must also pay £44 500 on “ineligible”
works (low-level work and contingencies not
grant-aided by English Heritage but which we
must carry out). The VAT on these comes to £7
800, which we will reclaim and retain.
Costs (including VAT and
architect’s fees), based on tenders accepted
November 2003:
Spire/tower repairs and re-leading high-level
roofs £164 000
Re-leading porch roof (Nov. 2002) £ 4
500
Ground works (see Progress Report 1) £
20 000
Contingencies (see Note 3) £ 23 000
TOTAL £211 500
Note 2: E. & O.E. All figures
are rounded to the nearest £100. Costs
and estimates are liable to change as the months
pass - especially the cost of re-roofing the
aisles and transepts, which have not yet been
de-leaded but could well show the degradation
of timbers revealed by the de-leading of the
nave.
Projected shortfall at 9 December 2004 £
16 100.
Note 3:
This figure for the shortfall is very optimistic
but is the best we can do at the moment. We
have already had to spend all the sum allocated
above for Contingencies. When the roofs of the
aisles and transepts have been stripped and
the state of the woodwork evaluated we expect
costs to rise, even possibly to the extent of
not being able to afford to re-roof one of these.
Work completed ( these
timings are approximate and a guide only).
July 2004: Scaffolding erected
and temporary roof begun.
August 2004: Temporary roof over
nave erected.
Tower works begun.
September 2004: Tower work completed.
Tower scaffolding partly dismantled (the rest
later).
October 2004: Nave roof lead removed,
exposing underlying roof timbers.
Treatment or removal of rotten wood begun.
November 2004: Roof timbers being
replaced as required.
December 2004: Re-leading due
to start, after completion of timber repairs.
February 2005: Re-leading of the
nave roof due to be completed.
April 2005: Work on the aisles
and transepts due to be completed.
Then the ground works begin.
ROOF FUND APPEAL PROGRESS REPORT 1
UP TO 10 JULY 2004
St Peter and St Paul, Exton, Rutland
Historical Background.
Though parts of the church date from the 13th
and 14th centuries the spire was struck by lightning
in 1843 and much of the west end of the building
was destroyed. Stonework fell through the roof
of the nave and much damage was done to the
windows. The present roof and much of the tower
date from the mid-19th century and both, after
a century and a half, are in poor condition.
Water has got into the tower stonework (causing
extensive cracking and other damage) and the
roof leaks beyond the “patching will cure
it” stage.
The Appeal.
In April 2002 the Bishop of Peterborough led
a Service of Dedication of the then recently-restored
monuments.
(Note: the cost of the work, nearly £100
000, was borne by the Exton Monuments Restoration
Fund, a Registered Charity, financially completely
independent of the Parochial Church Council.
None of the small surplus has been given to
the Roof Fund. The lighting of the monuments
won an award).
At the service the Bishop announced the start
of an Appeal to re-roof the church. In August
2002 we were able to stage a (village) Public
Launch of the Appeal. We set ourselves for 2003
the target of “one local fund-raising
event each month on average” and in fact
managed 13 of these in that year. Some were
large (Auction of Promises £1330, Casseroles
by Candlelight £660, Bridge Day £670);
some were small; some were shared with other
groups; all kept the Roof Fund in the public
eye. We reduced the target for 2004 - there
are limits to what a community of about 240
households can manage without overkill - but
since our start in 2002 donations and fund-raising
events have brought in nearly £9 000.
We are doing our best!
Committee and Architect.
The members of the Committee, which is a sub-committee
of the P.C.C. and reports to it regularly, are:
Patron: The Rt. Hon. The Earl of Gainsborough.
Chairman - T.C.Swinfen MA BSc FRSC, Deputy Churchwarden
(Churchwarden 1994-2002) and formerly Head of
Science, Uppingham School, Rutland.
Secretary - Mrs Lynda Hamilton BA (formerly
Languages Dept., Oakham School, Rutland).
Treasurer - Colin H Hagger (formerly Bank Manager,
Barclays Bank, London)
Committee - Mrs Patricia S Hagger, Churchwarden
(formerly Bank Manager, Barclays Bank, London)
- Mrs Judith Swinfen, Secretary of P.C.C. (freelance
artist).
Architect: Peter McFarlane B.Sc, B.Arch, Dip.Cons,
RIBA, 19 North Parade, Grantham, Lincs NG31
8AT.
Tel: 01476-564049 Fax 01476-592416.
Planning.
English Heritage awarded us a Stage 1 Grant,
essentially to find out what needed to be done,
what it would cost, etc. We sent the relevant
documentation to EH comfortably before its deadline.
This study was completed to the satisfaction
of EH. Stage 1 cost £12 906, of which
the EH grant covered £9 680 and Exton
PCC Roof Fund the rest. This brings us to the
end of 2003.
English Heritage has increased our Stage 2 Grant
to reflect increased costs since 2002 and extra
work (e.g. a temporary roof) which EH decided
is necessary. The new grant is £129 000,
an increase of £32 600, for which the
Committee is grateful.
In a recent Budget the Chancellor of the Exchequer
announced that for works such as ours VAT could
be reclaimed completely. The EH grant includes
payment of VAT covered by its grant (i.e. some
£18 000) but we hope to claim back the
rest.
Costings.
All subsequent figures are rounded to the nearest
£100 and were correct at 10 July 2004
unless otherwise stated. The Architect’s
estimates made in 2002 are inevitably lower
than the actual tenders of November 2003.
Cost of the project (including
VAT and architect’s fees).
Spire/tower repairs and re-leading high-level
roofs £164 000
Re-leading porch roof (Nov 2002) £ 4 500
Contingencies £ 20 000
Ground works £ 20 000
(These are works required by English Heritage
as a condition of receiving the grant above
but not grant-aided by EH. They involve the
altering of surrounds and channels at the foot
of the walls and the replacing of the oil tank.
We are allowed to do this after the scaffolding
has been taken down, which is manifestly sensible,
but to omit the works is not an option.)
Total cost of this project £208 500
Funds raised (including
firm promises) at 10 July 2004.
Fund-raising and donations within the parish
£ 8 800
English Heritage Stage 2 Grant £129 000
Grants and promises from Foundations, Funds
and Trusts:
The Alan Evans Memorial Trust
The Allchurches Trust
The Chase Charity
The Cory Environmental Trust
The Francis Coales Charitable Foundation
The Garfield Weston Foundation
The Headley Trust
The Historic Churches Preservation Trust
The Jill Franklin Trust
Rutland County Council
The Rutland Historic Churches Preservation Trust
The Trusthouse Charitable Foundation
The Wolfson Foundation/Council for the Care
of Churches
£ 40 200
Less Exton PCC contribution towards English
Heritage Stage 1 (£ 3 200)
Shortfall at 10 July 2004 £ 33 700
Note: this does not take into account repayment
of VAT on the work that we, as opposed to English
Heritage, must pay for: 25% of the high level
work and all of the rest. At this stage we are
guessing at the figure but it could reduce the
deficit by perhaps £10k.
We have applied for a grant from the Mercers’
Company. We will apply to any possible sources
of help.
The work.
The contractors are K.G.Wright (Builders) Ltd.
of Islip, Thrapston, Northants.
We had hoped to begin work in March 2004 but
the need to get everything right with English
Heritage and the Diocese forced us to hold fire.
In the light of the Budget this delay was fortunate.
The scaffolding is now being erected. Work on
the tower has begun, to be followed by the roof,
and should end in March 2005. The ground works
will then follow.
Further works.
It may be tempting Providence to list here future
plans, but it would be sensible to do so. (Costs
estimated November 2002)
Bell frame repairs (our ring of six bells is
out of action until this work is done) £
4 000
Churchyard north gateway and nave east gable
£ 2 000
Extensive window releading £ 20 000
General stonework repairs £ 4 000
Total £ 30 000
This report is now frozen and Progress Report
2 will carry reports of progress from August
2004 onwards.